The expansion works of the eight kilometre-long six-lane approach road of Shah Amanat bridge over the river Karnaphuli is progressing fast aiming to open it for traffic before impending Eid-ul Fitr.
The bridge connecting road consists of five kilometres on city side of Baddarhat intersection and three kilometres on the south side of Shah Amanat bridge. The expansion work on south side is nearing completion including final touch of the carpeting.
During Eid vacation, the commuters, specially home-bound people of south Chattogram, Bandarban and Cox’s Bazar will get advantage of six lane road facilities while city residents on the part of Baddarhat intersection will also avail the easier advantage of communications than the existing one, reports BSS.
This correspondent after visiting the Baddarhat intersection part of the approach road, found that the bitumen works is progressing fast where the earth filling and related works are almost completed.
The expansion works in city part is undergoing round the clock aimed at relieving the miseries of the home going people of the South Chattogram, Bandarban and Cox’s Bazar district.
Project Director (PD) Tofail Mia of roads and highway said they are trying putting utmost efforts to provide better communication facilities through Shah Amanat bridge connecting road on both sides of the bridge on Eid vacation.
The PD who is also an executive engineer of roads and highway hoped no home bound people will have to face miseries in journey through approach road.
Tofail said the works of Asphalt plant in Karnaphuli thana portion is almost completed and the different modes of vehicles will easily ply without any hindrances.
Deputy Project Manager Engr Ashik Kadir said that nearly 80 per cent project works of eight kilometre-long approach road have already been completed including constructions of eight concrete culverts and four bridge sub-structures.
The under construction Rahattar pool bridge is expected to open to traffic before Eid festival, he added.