SC orders status quo on eviction of illegal structures from Hatirjheel


FE Team | Published: November 07, 2022 17:37:25 | Updated: November 07, 2022 18:16:17


SC orders status quo on eviction of illegal structures from Hatirjheel

The Appellate Division on Monday ordered maintaining the status quo on the eviction process of the unauthorised commercial establishments at the Hatirjheel-Begunmari project.

A five-member bench of the Appellate Division led by Chief Justice Hasan Foyez Siddiqui passed the order. It said the status quo will remain in force until the disposition of the leave-to-appeal petition filed by Rajuk against the High Court order, according to UNB.

Now, no drive will be conducted to evict the commercial establishments in the Hatirjheel area until further order.

Attorney General AM Amin Uddin and Barrister Imam Hasan stood for Rajdhani Unnayan Kartripakkha (Rajuk) while Senior Advocate Manzill Murshid represented the petitioner.

On May 24, the High Court issued four directives terming the Hatirjheel area including the Begunbari canal as an asset of the state and declaring all commercial establishments there including hotels, restaurants and shops in the project area illegal.

The court also gave nine suggestions including the formation of a separate authority for the preservation, development and management of the Hatirjheel-Begunbari project, appointing Buet and the 24th Engineering Construction Brigade of the Bangladesh Army as permanent consultants for the project, constructing international standard underground toilets for public use, arrangement of drinking water for free, constructing separate roads for walking, movement of the by-cycle lane and physically challenged people, imposing a ban on motorised water vessels which is harmful to water.

On September 9, 2018, Human Rights and Peace for Bangladesh (HRPB) filed the writ petition with the High Court.

On September 10, 2018, the High Court issued a rule asking the authorities concerned to explain why directives should not be given to stop the construction of structures beyond the layout plan of the project and protect the project as per the design.

On June 30, last year, the High Court declared all commercial establishments including hotels, restaurants and shops in the Hatirjheel-Begunbari area illegal and ordered their eviction in 60 days.

The full text of the verdict was published on May 24. Later, Rajuk filed a leave-to-appeal petition against the High Court order.