Loading...

Matarbari power plant to go for trial run in December

| Updated: January 21, 2023 15:54:32


Matarbari power plant to go for trial run in December

Matarbari power plant will go for experimental electricity generation in December this year, said State Minister for Power, Energy and Mineral Resources Nasrul Hamid.

"Initially one unit having 600 MW power generation capacity will go for experimental operation in December and commercial commissioning will be in January next year (2024)," he said while visiting the power plant and Single Point Mooring (SPM) on Thursday.

Nasrul Hamid said engineers and technicians from Japan were engaged to construct Matarbari ultra-supercritical coal-fired power plant having 1200 MW electricity generation capacity, reports BSS.

He said that another unit with 600 MW generation capacity will come into operation in June-July, 2024.

The state minister said the overall progress of the power plant rose to 75 per cent, adding, "We hope that 1200 MW power will come from the plant in 2024."

He inspected the construction work of the plant, port and SPM and gave instructions for completing those projects on time and maintaining quality.

Seema Hamid, a social worker and wife of Nasrul Hamid accompanied the state minister during the visit.

According to the project details, the Matarbari power plant constructed a jetty for unloading coal and silos to store coal for 60 days. The plant will need 13,104 tonnes of coal per day for generating electricity.

Mother vessel with 80,000 tonnes of coal will be able to anchor at the jetty, while only 1-2 days will be needed for unloading the coal from the vessel.

A 14.3 km long (300 m wide) channel was prepared to ease the movement of the mother vessel at the power jetty, while measures were taken to ensure the navigability of the channel through a sedimentation mitigation dyke.

A study showed that there was a potential of 8.0 million tons of sediment deposition per year. Authorities constructed two separate ash ponds for ash management properly.

The power plant is being built adjacent to the sea, which will not be affected by cyclones or tides, as a 14-meter-above sea-level embankment was constructed and the power plant is located inside the dam keeping in mind the highest tide in Bangladesh at a height of 10 meters. The 1991 cyclone caused a 7-meter high tide.

Nasrul Hamid said that the overall physical progress of the project is 75 per cent, and financial progress is 57 per cent. The physical progress of the Port and Power plant is 88 per cent. Construction of 275 m high chimney was completed, while the boiler, turbine generator and auxiliary works of pre-commissioning are in progress.

"We expect the first unit of 600 MW to be commissioned in December next year, and the second unit (600 MW) to come into commercial production 6 months later," he added.

The state minister said that there will be a land-based LNG terminal as well as an LNG-based power plant instead of coal.

"We have decided to build an LNG terminal here to ensure energy security. The expert team has visited the site and the work will start soon. It will take about four years from the start of work," he said.

Earlier, a loan agreement was signed between the government and Japan International Cooperation Agency (JICA) on 16 June 2014. Under the deal, JICA will give Tk 439.21 million as project support, while the remaining Tk 79.33 million be provided by the Bangladesh government and CPGCBL.

A consortium of Japan's Sumitomo Corporation, Toshiba Corporation and IHI Corporation has been working as the EPC contractor for the Matarbari 1200 MW ultra-supercritical coal-based power plant project.

Share if you like

Filter By Topic