Loading...
The Financial Express

DNCC's U-loop project hits snags at start on land acquisition hurdles

| Updated: November 18, 2017 20:08:34


U-loop hits snags at start

A project of Dhaka North City Corporation or DNCC to set up 11 U-loops at the key points of the street from Saatrasta to Uttara in Dhaka has hit a road bump at the very start over land acquisition complexities.

The DNCC had put SM Constructions on the job to set up the U-loops on October 29 with an aim to ease traffic congestions in the capital.

The contractor says the Roads and Highways Department or RHD has created the obstacles by not clearing the land.

The project director fears that it will not be possible to complete the scheme in time, as they are yet to get the land.

The U-loops will be set up at Saatrasta, Kohinoor Chemical intersection, Mohakhali Bus Terminal, Mohakhali Flyover, Banani Chairmanbarhi, Banani Graveyard, Banani Overpass, Shewrha, Kaola, in front of Uttara RAB-1 offices, and near Jasimuddin Road.

The estimated cost of the project is Tk 248.3 million. The government is providing Tk 198.64 million while the city corporation will fund the remaining Tk 49.66 million.

During site visits on Thursday and Friday, workers were demolishing pavements and other structures at Kohinoor Chemical, Mohakhali Bus Terminal, Banani Chairmanbarhi, Banani Graveyard, Banani Overpass, and Uttara RAB-1 offices points.

SM Constructions Managing Director Hasibur Rahman Shaheen said they could not start the work in some other areas as the RHD and Land Record and Survey Department have not cleared the land.

"Roads department has some land there. They are creating problems. They don't want to clear the land from the airport to Banani for beautification," he said.

"They are making needless delays. The U-loops will be set up in time where we have got the land. But how will we work at the remaining points?" he asked.

He said people at the Bus Rapid Transit or BRT and Elevated Expressway projects were hindering the work at Uttara and Banani Graveyard points respectively, reports bdnews24.

The DNCC sent the U-loop project for approval to the Planning Commission by the end of last November. It proposed to start the work by December last year and complete it by June this year, but the commission approved it in March this year.

Later, the Local Government Division approved an extension of the project until June 2018 on the city corporation's wish.

The DNCC said it needed time to remove the structures and acquire the land. However, the estimated cost remained the same.

Project Director Khandaker Mahbub Alam said the RHD was demanding compensation for the 1.36 acres of land.

He alleged the RHD had not asked for the money before the project was taken up but raised the demand when the work started.

"We contacted different agencies after initiating the project in September 2015. Many letters have been traded.

“The project was discussed at a meeting attended by the road transport secretary. We were asked to submit a demand note on the necessary land, including the design, at the meeting. We did so," he said.

"We started the work after the meeting. Our contractor is on the sites now. Now they are saying that we'll have to buy the land," he added.

Mahbub said they were yet to get permission to use the government land for the project. "It will be difficult to finish the project in time if we don't get the permission," he said.

RHD Executive Engineer Mohammad Mahade Iqbal said they had set a condition for the DNCC to pay for removing the structures of the department.

"We've made a report on the estimated damages for those structures. We will submit it to the city corporation next week.”

He also said the DNCC would not be allowed to set up U-loops from the airport to Abdullahpur as the land has already been allocated for the BRT project.

"They have initiated a project for two to three years while we are thinking about a permanent system. We can't give them land which is already designated for another project," he said.

Two of the proposed U-loops are situated between the airport and Abdullahpur.

BRT Project Director Sanaul Haque said the proposed U-loop in front of the RAB-1 offices would have to be removed once the BRT project was implemented.

"There won't be any problem with the other near Jasimuddin Road as we will build a flyover there," he added.

Share if you like

Filter By Topic